NOMST is a system developed by the Nippon Steel Corp. It consists of light weight aggregate concrete reinforced with carbon/epoxy cables that serve as lateral walls for shafts used to initiate tunneling with closed type shields (bores). Shields are commonly used for tunneling in soft soil with high groundwater pressure. The tunnel is initiated through lateral shaft walls fabricated from reinforced concrete, steel sheet-piles, and soil cement with H-beam piles. Cutting through the lateral wall into the strata behind it requires that the soil immediately behind the lateral wall be improved. One of a number of techniques shown in Fig. 3.113 can be used to prevent ground loss, excessive ingress of water into the shaft or settlement of the surface. This slows down progress and is also fairly expensive. In addition, as the shield cuts through the wall, its drill heads are severely damaged by the reinforcing steel in the lateral wall, resulting in further expenses and delays in tunneling. NOMST provides a cost-efficient means of significantly reducing damage to the shield in addition to not requiring any improvement of soil strata behind the lateral wall, providing a faster and cheaper construction method.
In this system, the portion of the lateral wall through which the tunnel is to be driven is fabricated using a special grade of lightweight concrete reinforced with cables formed of carbon/epoxy rods. The section is fabricated as precast panels (Fig. 3.116). The precast sections can be used as part of a caisson (which is sunk into place), or installed into trenches excavated to the required depth. Once the panels are placed in the trenches, the trench is filled with slurry to form a wall. The shaft is the excavated on its inside face (Figs. 3.114-115).

Fig. 3.113. Soil improvement methods for shield initiation.

Fig. 3.114. Stages in the positioning of a NOMST section.

Fig. 3.115. Insertion of a NOMST panel into a shaft.
Fig. 3.116. Details of a NOMST section.
Once the shaft is excavated, the walls are built up for stability, except the area with NOMST through which the tunneling is to be initiated. In this area, a special socket is installed to serve as a positioning device for the shield head, and retains the water pressure between the socket and the lining (Fig. 3.117-118).

Fig. 3.117. Schematic showing shield and NOMST.

Fig. 3.118. View of initiation
socket and shield.
To facilitate good strength and ease of cutting by the shield, a special lightweight aggregate (mesalite, limestone and/or basalt) is used with concrete mixes designed for 28-day strengths ranging from 46 N/mm2 to 86.6 N/mm2. Carbon fibers impregnated with epoxy to form 4.4 mm diameter rods are used in cables containing 37 strands with an overall diameter of 30 mm. Properties of individual rods and the cable are shown in Table 3.27.
Material Form | Diameter (mm) | Cross-Sectional Area (cm2) | Tensile Strength (kN) | Elastic Modulus (kN/mm2) |
Rod 37 Rod Cable | 4.4 30 | 0.152 5.383 | 23.52 457.66 | 205.8 166.6 |
As shown in Fig. 3.116, the constraining reinforcement in the NOMST section is also fabricated from carbon fiber reinforced epoxy rods.
In addition to its use as a reinforcing layer in a vertical wall, NOMST systems can also be used in other configurations such as in walls of tunnels between which a connection tunnel is to be built, tunnel arches through which vertical shafts are to be constructed, and along tunnel walls from which new tunnels are to be constructed.
The system has been successfully used in over 36 projects to date (listed in Table 3.28). The first project listed, the March 1993 Nagota electric cable-pipeline, was constructed in water bearing gravel strata using a 25 cm thick NOMST panel for a shield diameter of 2,930 mm at a cutting rate of 2 mm/min through the wall,
Client | Project | Contractor | Shield | Condition at Shield Opening | Water | Walls | Secondary | Size | Date | ||
& Site | Machine (Type &/or Make) | Dia. of shield (mm) | Depth at center of opening | Soil behind shaft wall | Pressure (kgf/cm2) | of Shaft | Operation | of Panels (mm) | |||
The Tokyo Electric Power Co., Inc. | Nogata District Electric Cable-Pipeline | Hazama, Fujita, Dainihon-doboku JV | Hitachi Kenki Co., Ltd. | 2930 | 6 m | Sand and gravel layer | 0.3 | Mud soil wall t=500 mm | None | B: 250 H: 250 L: 11,000 | 9/92 |
The Tokyo Electric Power Co., Inc. | District H Pipeline Works | Hazama, Okumura, Chisaki JV | Hitachi Kenki Co., Ltd. | 3540 | 11 m | Sand layer, Yura-kucho layer | 1 | SMW f650 mm ctc 450 mm | None | B: 250 H: 530 L: 5740 | 6/93 |
Yokohama City | Seyaiida District Drainage Main Line | Hazama, Chisaki, Katsumura, Ishida, JV | Nippon Kokan, K.K. | 4180 | 33 m | Sand and gravel, clay layer | 1.8 | RC wall t=1200 mm | None | B: 550 H: 800 L: 9935 | 7/93 |
Bureau of Sewage Works, Tokyo Prefct. | Nansa Main Line Shaft Works | Nishimatsu, Obayashi JV | IHI Co., Ltd. | 1) 3930 2) 3480 3) 3680 | 12 m | Clay layer, Yura-kucho layer | 1 | SMW f650 mm ctc 450 mm | None | B: 300 H: 440 L: 6530 | 9/93 |
Japan Sewage Works Public Corp. | Yokohama City Suehiro Sewer Branch Line Works | Kumagai, Konoike, Koukankoji JV | Mitsubishi Heavy Industries, Ltd. | 4690 | 67 m | Mud/stone layer | 5 | RC wall t=1200 mm | None | B: 500 H: 700 L: 6300 | 6/93 |
Tokyo Prefecture Subway Construction Co., Ltd. | Subway #12 Line, Roppongi Aoyama District | Hazama, Aoki, Ito, Aizawa, Tokukura JV | Hitachi Shipbuilding & Engineering Co., Ltd. | 5440 x 2 | 26 m | Sand layer | 1.5 | Mud soil wall t=600 mm | None | B: 700 H: 480 L: 10,740 | 12/93 5/94 |
Tokyo Prefecture Subway Construction Co., Ltd. | Subway #12 Line, Shiodome Hamamatsu-cho District | Kajima, Takenaka-doboku, Nihon-kokudo, Wakashkiu, Nara JV | Kawasaki Heavy Industries, Ltd. | 5440 x 2 | 23 m | Sand layer | 2.0 | Mud soil wall t=800 mm | None | B: 520 H: 620 L: 8720 | 2-3/94 |
Japan Railway Construction Corp. | Minatomirai Chuo Station Ookagawa T Works | Taisei, Chisaki, Goyo JV | Kawasaki Heavy Industries, Ltd. | 7300 x 2 | 22 m | Clay layer | 1.9 | SMW f650 mm ctc 450 mm | None | B: 300 H: 500 L: 12,200 | 3/94 |
Teito Rapid Transit Authority | Eidan #7 Line, Azabu Station Project | Zenitaka, Misubishi JV | Hitachi Shipbuilding & Engineering Co., Ltd. | 6800 x 2 | 21 m | Sand layer | 2 | Steel wall (NS-Box) t= 900 mm | None | B: 860 H: 800 L: 11,000 | 5-7/94 |
The Kansai Electric Power Co., Ltd. | Nishimatsu, Obayashi, Maeda, Okumura JV | Nishimatsu, Obayashi, Maeda, Okumura JV | Kawasaki Heavy Industries, Ltd. | 1) 7260 2) 6850 | 33 m | Clay and sand layer | 2.4 | RC wall t=1300 mm | Max. 3 m grouting in front | B: 600 H: 900 L: 12,300 | 8/94 |
Client | Project | Contractor | Shield | Condition at Shield Opening | Water | Walls | Secondary | Size | Date | ||
& Site | Machine (Type &/or Make) | Dia. of shield (mm) | Depth at center of opening | Soil behind shaft wall | Pressure (kgf/cm2) | of Shaft | Operation | of Panels (mm) | |||
Admin. Division, Central Wholesale Market, Tokyo Prefct. | Party box culvert (#2) shaft project | Konoike-gumi | Misui Shipbuilding & Engineering Co., Ltd. | 1) 3500 2) 3500 | 15 m | Sand layer | 1.4 | SMW f650 mm ctc 450 mm | None | B: 300 H: 500 L: 6100 | 11/94 |
The Chubu Electric Power Co., Inc. | Niinabi #7 Series Gas Pipeline Works (#5 district) | Taisei, Konoike Shinnittetsu, Toda, Fudo JV | IHI Co., Ltd. | 3660 | 10 m | Mud-stone layer | 0.8 | SMW t=900 mm | Cut off by water glass | B: 300 H: 480 L: 6170 | 1/95 |
The Chubu Electric Power Co., Inc. | Niinabi #7 Series Gas Pipeline Works (#2 district) | Sato, Asuka, Nihon-kokuda, Taiho, Sumitomo JV | IHI Co., Ltd. | 4100 | 30 m | Clay and sand layer | 2.7 | Round caisson t=2100 mm | 2 m grouting in front | Rod f12.5 Rod f20 | 1/95 |
The Chubu Electric Power Co., Inc. | Nashiro Transformer Station Project | Shimizu, Kajima, Sato, Kumagai, Hazama JV | Mitsubishi Heavy Industries, Ltd. | 1) 4950 2) 4950 3) 5440 | 18 m 26 m 26 m | Sand layer | 1.8 | RC wall t=1200 mm | None | B: 615 H: 900 L: 12,300 | 2/95 |
The Chubu Electric Power Co., Inc. | Niinabi #7 Series Gas Pipeline Works (#3 district) | Shimizu, Hazama, Take-nakadoboku, Shinnittetsu, Shiraishi JV | Mitsubishi Heavy Industries, Ltd. | 4100 | 26 m | Sand and clay layer | 2.4 | Round caisson t=1800 mm | 2 m grouting in front | Rod f20 | 3/95 |
Osaka Gas Co., Ltd. | Hamadera Anchorage Shield | Konoike | Komatsu, Ltd. | 1) 3000 2) 3000 | 38 m | Sand and clay layer | 3.7 | RC & steel wall t=1000 mm | 5.8 m: CJG 7.9 m: CJG | B: 510 H: 580 L: 4700 | 2-5/ 95 |
Osaka Gas Co., Ltd. | Bay Line Shield | Zenitaka | Hitachi Shipbuilding & Engineering Co., Ltd. | 1) 3000 2) 3000 | 33.9 m | Sand layer | 3.1 | RC & steel wall t=1000 mm | CJG machine length 5 m | Rod f12.5 Rod f20 | 3/95 8/95 |
Bureau of Transpor-tation, Osaka City | Osaka Subway/ Tsurumi Ryokuchi Line Extension Works | Obayashi, Konoike, Sato, Okumura, Toyo JV | Hitachi Shipbuilding & Engineering Co., Ltd. | 5440 x 2 | 23 m | Diluvial sand and clay layer | 1.2 | RC wall t=1200 mm | 1.5 m grouting in front | B: 500 H: 750 L: 8740 | 5/95 |
The Chubu Electric Power Co., Inc. | Niinabi #7 Series Gas Pipeline Works (#6 district) | Obayashi, Kajima, Okumura, Shinnittetsu, Taihei JV | Kawasaki Heavy Industries, Ltd. | 4100 | 23 m | Clay layer | 2 | Round caisson t=2000 mm | Rod f12.5 | 5/95 | |
Teito Rapid Transit Authority | Shiragane Ventilation Room | Dainihondo-boku | Kawasaki Heavy Industries, Ltd. | 10,040 | 24 m | Mud solid wall t=800 mm | None | B: 530 H: 700 L: 12,480 | 5/95 | ||
Teito Rapid Transit Authority | Saitama Express Railway Kawaguchi Motogo District Works | Sata, Morimoto JV | Kawasaki Heavy Industries, Ltd. | 9700 | 18 m | Sandy silt layer | 1.6 | RC continuous wall t=1000 mm | None | B: 1000 H: 900 L: 11,720 | 5/95 |
The Tokyo Electric Power Co., Inc. | Loop #7 Tokai Matsubara Pipeline | Hazama, Mitsui, Toa, Toyo, Tekken JV | Kawasaki Heavy Industries, Ltd. | 7270 | 9.8 m | Alluvial silt layer | SMW f850, ctc 600 mm | None | B: 430 H: 700 L: 11,360 | 5/95 | |
Bureau of Transport., Yokohama City | Express Railway #1 Line Katsuno-kuchi District Works | Misui, Kudo JV | Hitachi Kenki Co., Ltd., Nippon Kokan, K.K. | 1) 7150 2) 7150 | 12.5 m | Clay layer | 0.7 | SMW f650 ctc 450 mm | None | B: 300 H: 500 L: 9800 | 6/95 |
Tokyo Gas Co., Ltd. | Tokyo Gas / Yokohama | Kumagai, Haseko, Nara JV | Kawasaki Heavy Industries, Ltd. | 1) 4290 2) 2290 | 17 m | Mud-stone layer | Round caisson t=1000 mm | Rod f12.5 Rod f20 | 6/95 | ||
Client | Project | Contractor | Shield | Condition at Shield Opening | Water | Walls | Secondary | Size | Date | ||
& Site | Machine (Type &/or Make) | Dia. of shield (mm) | Depth at center of opening | Soil behind shaft wall | Pressure (kgf/cm2) | of Shaft | Operation | of Panels (mm) | |||
Bureau of Sewage Works, Yokohama City | Matano Drainage Main Line | Hazama, Ishida, Kojaku JV | Sumitomo Heavy Industries, Ltd. | 3680 | 15 m | Sand and gravel layer | Round caisson t=600 mm | None | Rod f12.5 | 7-8/ 95 | |
The Chuba Electric Power Co., Inc. | Niinabi #7 Series, Diversion Channel Tunneling Works | Kajima, Nishimatsu, Maeda, Toda, Mitsui JV | Kawasaki Heavy Industries, Ltd. | 8160 | Round caisson t=1500 mm | None | Rod f12.5 | 7/95 | |||
Ministry of Construction | Ministry of Construction Kasumigaura Takahama | Taisei-kensetsu | 1) 5810 2) 5810 | 32 m | Sand layer | 3 | Round caisson t=1800 mm | 1.5 m grouting in front | Rod f12.5 Rod f20 | 7-8/ 95 | |
Teito Rapid Transit Authority | Eidan #7 Line, Kiyomasako District | Hazama, Fudo JV | 6800 | 28 m | Sand, gravel, clay layer | 2.3 | Mud solid wall | None | B: 530 H: 1000 L: 8520 | 8/95 | |
The Tokyo Electric Power Co., Inc. | Sekido, Gyokou Bridge | Hazama | Sumitomo Heavy Industries, Ltd. | 2830 | 11 m | Sand layer | 0.9 | PIP | 1.8 m CJG in front | B: 300 H: 370 L: 4210 | 10/95 |
Kyushu Electric Power Co., Inc. | New Oita Power Plant 3-1 Series Diversion Channel Works | Asuka, Kajima, Fudo JV | Kawasaki Heavy Industries, Ltd. | 1) 6000 2) 6000 | 11 m | Sand layer | 0.8 | SMW f650 ctc 450 mm | 1.5 m CJG in front | B: 300 H: 500 L: 8495 | 11/95 10/95 |
Osaka Gas Co., Ltd. | Tenpozan Offshore | Obayashi, Kubagai, Fujita, Fudo JV | 3050 | 56 m | Clay layer | 5 | Steel wall | Freeze opening | B: 558 H: 800 L: 4950 | 12/95 | |
Osaka Gas Co., Ltd. | Nanko Shield | Shimizu, Kajima, Okumura, Mitsui JV | Hitachi Kenki Co., Ltd. | 3000 | 41 m | 3.7 | RC wall | 8 m CJG & grout | B: 400 H: 670 L: 9340 | 12/95 | |
Japan Railway Construction Corp. | Saitama Express Railway, Araijuku Station (end point) | Mitsui, Fukuda, Mitsubishi JV | 9700 | 13.3 m | Sand layer | 0.9 | SMW f850 ctc 600 mm | None | B: 430 H: 710 L: 12,900 | 12/95 | |
Japan Railway Construction Corp. | Saitama Express Railway, Higashi Kawaguchi Station (end point) | Asuka, Wakana, Totetsu JV | 9600 | 15.2 m | Clay and sand layer | 1.3 | SMW f850 ctc 600 mm | None | B: 430 H: 710 L: 12,110 | 2/96 | |
Japan Railway Construction Corp. | Joban New Line, Nishi Ayase T Works | Dainihon, Asanuma Chisaki JV | 10,600 | 12.5 m | Clay layer | 1.1 | SMW f850 ctc 600 mm | None | B: 430 H: 700 L: 14,300 | 3/96 | |
Bureau of Sewage Works, Tokyo Prefecture | Shingashigawa Disposal Plant Pipeline #4 End Shaft Works | Obayashi, Hazama JV | 5540 | Round caisson t=1500 mm | None | Rod f12.5 | 5/95 | ||||