Ground anchors consisting of cables or rods connected to a bearing plate are often used for the stabilization of steep slopes or slopes consisting of softer soils, as well as the enhancement of embankment or foundation soil capacity, or to prevent excessive erosion and landslides. The use of steel ground anchors is often constrained by overall durability in placement (due to weight), and the difficulty in maintaining tension levels in the anchor. Anchor systems fabricated from fiber reinforced composite materials show a number of benefits compared to conventional systems for the following reasons:
In most cases, it is possible to use conventional jacking systems and still realize greater flexibility in placement and tensioning in difficult ground formations.
Composite ground anchors generically consist of three parts:
Four different composite ground anchor systems are available.

Fig. 3.101. Leadline type anchor system.

Fig. 3.102. CFCC type anchor system.
Table 3.25 provides a comparison of these different systems.
The components of a Technora aramid ground anchor are shown in Fig. 3.103. The front/top end consists of a stainless steel anchorage fixed to a bearing plate using nuts (which make initial tensioning and subsequent retensioning simple). The anchorage is filled with a non-shrink mortar. The free anchor length is enclosed in a polyethylene sheath joined to the anchorage protection pipe that extends beyond the filled anchorage section. Individual rods along the fixed anchor length are held together by plastic grips. The ends are enclosed in an end anchorage similar to the front anchorage. The entire system is fitted into a predrilled hole in the soil, which is then filled with grout.
Leadline | CFCC | FiBRA | Technora | ||
GA-D8 | GA-D10 | ||||
Nominal Strand Diameter (mm) Nominal Cross-Section (mm2) Number of Individual Strands Matrix Fiber Volume Fraction (%) Tensile Force (kN) Tensile Strength (GPa) Tensile Modulus (GPa) Extension at Failure (%) Coefficient of Thermal Expansion (x 10-6 / 0C) Specific Gravity Unit Weight (g/m) | 8 46.1 9 Epoxy 65 120 2.6 147 - 160 1.6 0.68 1.6 77 | 10 71.8 9 Epoxy 65 186 2.6 147 - 160 1.6 0.68 1.6 118 | 12.5 76.0 7 (Twisted Together) Epoxy * 142.2 1.8 137 1.6 0.6 1.5 151 | 10.4 85.0 Braided Rod Epoxy * 117.7 * 68.6 2.0 * 1.3 * | 7.4 43.0 9 Vinylester 65 86.2 2.14 52.9 3.8 -3.0 1.3 50.6 |

Fig. 3.103. Details of an aramid ground anchor system.The jacking/tensioning of individual anchors is shown in Fig. 3.104. The components of a "Leadline" ground anchor system are shown in Fig. 3.105. The anchors at the front and at the end are both made of stainless steel and use an expansive non-shrink mortar. Set loss in the system is accounted for by using the tensioning nuts that facilitate adjustment through the service life of the system. The anchor system is inserted into a bore hole, whose diameter varies between 115 mm and 170 mm, depending on the designed anchor force and the prevalent ground conditions. A flowchart showing details of the installation procedure is given in Fig. 3.106 along with diagrams showing details of some of the steps.

Fig. 3.104. Jacking of Technora ground anchors.

Fig. 3.105. Components of a "Leadline" ground anchor system (all dimensions in mm).

Fig. 3.106. Flowchart of the installation process.
A list of some application sites showing anchor types, locations and dimensions is given in Table 3.26 (p. 83). Some examples are described in more depth below.
During the widening of the Kajiwara section of the Meishin Expressway near Osaka, a test section was used to validate the efficacy of using Technora ground anchors for slope stabilization. The site had electric pylons located at the crown of the slope, necessitating the stabilization of the slope to prevent future deformation. Thirty six anchors were installed at the site using bundles of 9 spiral wound rods of 7.4 mm diameter each. This configuration achieved a design stabilization force of 400 kN in a strata consisting of a top layer of weathered soil 3 to 5 m deep, covering a fractured zone of slate. Anchors 19 m to 30 m long were placed as shown in a representative cross-section in Fig. 3.107. The anchors (6.5 m long) were fixed in the slate layer in holes with a bore diameter of 115 mm. After completion of construction in September 1994, lightweight composite pressure plates were used at the surface as shown in Fig. 3.108. A variety of other, non-composite ground anchoring systems were also tested at the same site as part of an overall test program conducted by the Japan Highways Corp. and the Osaka Construction Bureau.

Fig. 3.107. Representative cross-section of slope.

Fig. 3.108. Meishin Expressway site showing composite pressure plates used with Technora ground anchors.
In 1995, the Ministry of Construction commissioned the use of Technora aramid ground anchors in a pilot project. The aim was the technical certification of the system along the Kosedo section of a national road in the Kumamoto Prefecture. Road construction and related slope stabilization was necessary because of the rerouting of a section of the national highway due to construction of the Kawabe Dam. Sixty-five aramid ground anchors were used with lengths ranging from 7.8 m to 11 m along a section 30 m long and 8.5 m high. The top strata was a gravely soil to a depth of 4 m, below which was soft rock. Each ground anchor consisted of 9 deformed aramid rods of 7.4 mm diameter, each with a designed tensile load capacity of 392 kN. The anchor plates were set into a grid of reinforced concrete as shown in Fig. 3.109.

Fig. 3.109. Slope along the Kosedo section of the National Highway stabilized through the use of Technora aramid ground anchors.
CFCC ground anchors consisting of 7 12.5 mm rods were used for stabilization of a newly constructed slope along the Abuta section of the Jukan Highway in Hokkaido.

Fig. 3.110. Site with CFCC ground anchors.
The site used 28 ground anchors affixed to specially designed concrete pressure caps (Fig. 3.110) using a 6-piece stainless steel anchor clamped together as shown in the cross-section in Fig. 3.111.

Fig. 3.111. Representative section showing details of placement of the CFCC ground anchor.
Thirty two Leadline ground anchors (9 rods of 8 mm diameter each) were used to provide the anchorage for the stress ribbon bridge built for the Southern Yard Country Club. The anchors were post-tensioned through the concrete abutments as shown in the schematic in Fig. 3.112. Anchors were initially stressed to 80% of ultimate strength, which reduced to 70% at transfer for a final level of 60% under design load. Average anchor length was 26.5 m.

Fig. 3.112. Schematic showing placement of Leadline ground anchors in the Birdie stress ribbon bridge.
Table 3.26 lists examples of ground anchor applications.
Structure and Location | Owner | Date Completed | Anchor Type and Details | Anchor Length (m) | Total Length (m) | Stress Levels |
Birdie Bridge Ibaraki Prefecture | Southern Yard Country Club | 9/90 | Leadline (B-rib) 8 mm f (x9) 30 Anchors | Average = 26.5 | 7,150 | P1 = 0.8 P2 = 0.7 P3 = 0.6 |
Temporary Grade Shoring Kugawa Prefecture | Shikoku Japan Railways | 10/91 | Technora 6 mm f | 12 m | 500 | P1 = 0.7 P2 = 0.6 P3 = 0.6 |
Slope Stabilization Abuta Section, Jukan Highway, Hokkaido | Hokkaido Development Authority | 5/93 | CFCC 12.5 mm f (x7) | 24 m | 3,168 | P1 = 0.75 P2 = 0.6 P3 = 0.6 |
Snowbreak Slope Yatsukuchi, Niigata National Highway, Niigata Prefecture | Niigata Construction Bureau | 12/93 | CFCC 12.5 mm f (x7) | 10.7 - 10.88 | 2,699 | P1 = 0.75 P2 = 0.6 P3 = 0.6 |
Slope Stabilization Itoigawa-Tsutsuishi District, Niigata Prefecture | Niigata Construction Bureau | 2/94 | CFCC 12.5 mm f (x7) 4 Anchors | 16.5 | 198 | * |
Slope Stabilization Meishin Expressway Kajiwara Section, Osaka | Highways Corp. Osaka Construction Bureau | 9/94 | Technora Deformed Bars 7.4 mm f (x9) 36 Anchors | 19.0 - 30.0 | 8300 | P1 = 0.75 P2 = 0.6 P3 = 0.6 |
Maintenance of Structure Toyama Prefecture | Hokuriku Regional Construction Bureau | 12/94 | CFCC 12.5 mm f (x7) 6 Anchors | 11.0 14.5 17.7 | 133.5 | * |
Slope Stabilization Koseto District Kumamoto Prefecture | Kyushu Regional Construction Bureau | 3/95 | Technora Deformed Bars 7.4 mm f (x9) 65 Anchors | 7.8 -11 | 5160 | * |
Ground Stabilization for a Studio, Tokyo | Kodansha Co. | 9/95 | Leadline GA-D10L 10 mm f | 28.5 29.0 | 288 | * |
Ashiarai Revetment Gifu Prefecture | Hokuriku Regional Construction Bureau | 11/95 | CFCC 12.5 mm f (x7) 46 Anchors | 9.2 - 17.7 | 1467 | * |
Stabilization of Walkway for Asahi Primary School, Shizuoka Prefecture | Ito City Government | 11/95 | CFCC 12.5 mm f (x7) | 9.0 - 17.7 | 428 | * |
R156 Nazusa Improvement Gifu Prefecture | Chubu Regional Construction Bureau | 11/95 | CFCC 12.5 mm f (x7) | 7.59 - 10.59 | 770 | * |
Reinforcement of a Retaining Wall, Chiba Prefecture | Ichikawa City | 11/95 | Leadline, GA-D8L 8 mm f (x19) | 9.0 - 12.5 | 98 | * |
R160 Sazanami-Kurosaki Safety Works Ishikawa Prefecture | Hokuriku Regional Construction Bureau | 12/95 | CFCC 12.5 mm f (x7) 40 Anchors | 7.75 - 11.25 | 2244 | * |
R52 Nakano Safety Works, Yamanashi Prefecture | Kanto Regional Construction Bureau | 1/96 | CFCC 12.5 mm f (x7) 10 Anchors | 7.25 (max) | 218 | * |
Structure and Location | Owner | Date Completed | Anchor Type and Details | Anchor Length (m) | Total Length (m) | Stress Levels |
Slope Protection R9 Umetani District Kyoto | Kinki Regional Construction Bureau | 1/96 | CFCC 12.5 mm diameter (x7) 10 Anchors Leadline, GA-D88 mm f (x19) 243 Anchors | 7.25 - 17.25 7.20 - 21.20 | 244 5752 | * * |
Prevention of Landslide Soounzan, Kanagawa Prefecture | Odawara Civil Engineering Department | 1/96 - 3/96 | CFCC 12.5 mm f (x7) 1 Anchor | < 46 | 279 | * |
Stabilization of River Bank Benke Utashinai River Works, Hokkaido | Hokkaido Development Bureau | 2/96 | FiBRA FC11L 17 Anchors | 9.20 - 17.4 | 1000 | * |
Strengthening of Drainage Facility Omiya, Saitama Prefecture | Saitama Prefectural Government | 3/96 | FiBRA FC11L 13 Anchors | 21.90 - 27.4 | 2600 | * |
Miyonotsuji-Kamiyoshi Line Emergency Work, Kyoto | Shuzan Civil Engineering | 3/96 | CFCC 12.5 mm f (x7) 8 Anchors | 18.8 | 902 | * |
* = information not available